Skip to content

DCMA-14-Analyse

Where DCMA 14 comes from

The 14 point analysis originates with the Defense Contract Management Agency (DCMA), the contracting authority of the US Department of Defense. It was developed to establish quickly whether a submitted schedule can be assessed and steered at all. Since the publication of the "14 Point Schedule Assessment" the method has spread far beyond its origin. Today it is used in chemicals, pharma, energy and infrastructure as well.

One point matters for understanding it: the analysis assesses the structure of a schedule, not its substantive correctness. It answers whether a plan can calculate and forecast, not whether the planned activities make sense.

What the analysis examines

The 14 checks fall into three groups:

  • Network logic: are all activities linked, and do the links describe real dependencies (checks 1 to 4)?

  • Constraints and float: is the plan driven by imposed dates rather than logic, and is the float plausible (checks 5 to 9)?

  • Progress and forecast: is what was planned actually measured, and does the critical path support a prediction (checks 10 to 14)?

The 14 checks at a glance

No.

Check

Criterion / threshold

1

Logic

No more than 5 % of activities without a predecessor or successor

2

Leads (negative lags)

No negative lags between activities (0 %)

3

Lags

No more than 5 % of relationships carrying a positive lag

4

Relationship types

At least 90 % finish-to-start relationships

5

Hard constraints

No more than 5 % of activities with a hard constraint

6

High float

No more than 5 % of activities with total float above 44 working days

7

Negative float

No activity with total float below 0

8

High duration

No more than 5 % of activities with a remaining duration above 44 working days

9

Invalid dates

No actual dates in the future and no forecast dates in the past

10

Resources

Every activity with a duration greater than 0 carries resources or cost

11

Missed tasks

No more than 5 % of activities finishing later than in the baseline

12

Critical path test

An artificial delay on a critical activity moves the completion date by the same amount

13

CPLI (critical path length index)

At least 0.95

14

BEI (baseline execution index)

At least 0.95

The thresholds above are the DCMA reference values. In practice they are agreed per project: an expansion inside an operating plant has more imposed dates than a greenfield build, for good reasons. What matters is that deviations are justified and stay stable across the project lifetime.

How CEPT works with DCMA 14

We assess every schedule we take over before the first control cycle and in every update cycle after that. The results go into the project report as a fixed metric, so planning quality stays comparable over the lifetime of the project. Failed checks are not treated as a defect list but prioritised: whatever distorts the forecast is repaired first.

The assessment itself runs automatically; judging the findings remains expert work. A plan can pass all 14 checks and still miss the point of the project. Conversely, a plan failing several checks is virtually never steerable.

Frequently asked questions about DCMA 14

What is the DCMA 14 point analysis?

The DCMA 14 point analysis is a set of 14 checks for assessing the quality of project schedules, developed by the US Defense Contract Management Agency. It examines the structure of a plan (links, constraints, float, progress and forecast quality) rather than its substantive correctness. A plan that fails several checks can, as a rule, not be steered reliably.

Is DCMA 14 a certification?

No. There is neither a certificate nor an accrediting body; DCMA 14 is an openly documented assessment method. Clients can nevertheless require compliance contractually, and in large projects that is increasingly common.

Which thresholds count as passed?

The reference values include: no more than 5 % of activities without a predecessor or successor, no negative lags, at least 90 % finish-to-start relationships, and a CPLI and BEI of at least 0.95. These values come from the defence sector and are usually adjusted for industrial projects. More important than any single threshold is that deviations are justified and stable over time.

From what project size is the assessment worthwhile?

The assessment becomes worthwhile from roughly 300 to 500 activities, because structural errors in smaller plans can still be found by careful reading. With several trades, external interfaces or a multi-year duration it belongs in every update cycle. The effort per assessment is low once the analysis runs automatically.

Have your schedule assessed to DCMA 14

We assess your current schedule and discuss the findings with you, with prioritised actions instead of a defect list.